Sprint 8
- Start: 2021/02/08
- End: 2021/02/12
- Goal: Validate the everything nodes design with the lights of geometry nodes:
- Mapping out the use cases for the other node-based systems.
- On a high level, design how the different systems work.
- On a high level, design how the different systems integrate with each other.
Time
- Jacques: 4 days
- Pablo: 1 day
- Hans: 4 days
- Simon: 1 day
Impediments
Sprint Review
What went well
- Code review dynamic is working well.
- Satisfaction from mapping out the existing modifiers to help community involvement.
- More eyes in the same design problem (simulations) help to crack bigger problems or share the pain of the constraints of the solution.
- In person meetings about design went well although not strictly necessary.
- Focused, scheduled design time pays off.
What didn't go well
- Non-prioritized tasks took precedence over others, leading to a smaller throughput of the intended tasks.
- Meetings agendas was a bit hijacked with other topics, leading to important topics not to be addressed.
- Jacques didn't know how to approach big design so he wasn't so involved in the design topics.
- Mandatory meetings are taking too much time.
- Lack of past based scrum week combined with unknown design process lead to lack of big picture of the progress of the scrum.
Improvements
- Leave meetings when feel like it the presence not needed.